[Article Information]

Influence Analysis of New Tunnel Blasting on Lower Adjacent High-speed Railway Tunnel



YAN Tian-cheng ,ZHANG Qin-bin ,CHEN Min




Abstract


Abstract: The dynamic response of the lining structure of an existing tunnel during the blasting construction of a new tunnel is studied based on the Bogongao No. 1 tunnel project which belongs to one of the level 1 risk tunnels of Ganzhou-Shenzhen high-speed railway. The numerical model of the test section is established by using ANSYS /LSDYNA finite element software. By comparing the field measured with the model calculated vibration velocities,the reliability of the numerical simulation is verified with the inversed surrounding rock mass parameters. Furthermore, based on the parameters of the test section,a numerical model of the intersection of the two tunnels is further constructed,which is used to analyze the vibration attenuation law of the existing tunnel lining structure in the intersection,and put forward vibration reduction measures under the worst cases at the intersection. According to the research results,the largest vibration velocity appears at the vault of the existing tunnel and the smallest vibration velocity is at the floor. Within 30 m from the front and back of the intersection,the vibration velocity at the vault is about 2. 0 ~ 2. 3 times that at the side wall closer to the blast. For the whole section of the existing tunnel,the controlled vibration velocity of 1. 6 cm/s. However,for the side wall,the early warning value of vibration velocity should be 0. 8 cm/s. When the cut holes are bottom initiated,most of the explosion energy is transmitted to the unexcavated area,which contributes to a higher attenuation rate of vibration velocity from the excavated area of the new tunnel than from the unexcavated area. The blasting scheme of the test section is no longer applicable to the cross affected section. On the premise of considering both the work efficiency and blasting effect,the vibration velocity of the secondary lining in the existing tunnel can be controlled within the safe range after the footage is shortened to 1. 0 m and the cut hole charge is reduced to 9. 86 kg.



Key words: tunnel engineering; cross tunnel; dynamic response; numerical simulation; vibration reduction measures; vibration velocity contro





Chinese Information


标题: 新建隧道爆破对下部近接运营高铁隧道影响分析



作者: 颜天成 ,张庆彬 ,陈 敏



摘要: 以赣深高铁一级风险隧道———伯公坳 1 号隧道为背景,研究新建隧道爆破施工时,近接既有隧道 衬砌结构的动力响应。采用 Ansys/Ls-dyna 有限元软件建立试验段数值模型,将现场实测振速与模型计算振 速作对比,反演围岩介质参数,验证了数值模拟的可靠性。以试验段参数为基础,进一步构建了两隧道交叉 段的数值模型,由此分析交叉段既有隧道衬砌结构的振动衰减规律,提出交叉点处最不利工况的减振措施。 研究结果表明: 既有隧道拱顶振速最大,底板振速最小; 交叉点前后方 30 m 范围内,拱顶振速约为迎爆侧边 墙振速的 2. 0 ~ 2. 3 倍,1. 6 cm/s 的控制振速是针对既有隧道全断面而言的,因此其边墙部位的监测预警值 应取为 0. 8 cm/s; 掏槽孔反向起爆时,大部分的爆炸能量向未开挖区域传递,所以既有隧道对应于新建隧道 已开挖区域的振速衰减速率比未开挖区域的要大; 试验段的爆破方案不再适用于交叉影响段,在将进尺缩短 至 1. 0 m,掏槽孔药量减小至 9. 86 kg 后,能够在兼顾工效和爆破影响的前提下,将既有隧道二衬振速控制在 安全标准以内。



关键词: 隧道工程; 交叉隧道; 动力响应; 数值模拟; 降振措施; 振速控制



Journal Integrated Operation and Management Platform with Network JMPN-2.0
Journal Integrated Operation and Management Platform with Network

《Blasting 》editorial department
Copyright © 2009   System Management   Chinese
Statistical information:total visitors Online0
putting on ICP record: E-ICP Prepared No. 05003336-9