Experimental Study on Blasting Technology of Square Hole Layout with Deep and Shallow Holes under Condition of Hard and Soft rock Layers



WANG Hao-yong ,REN Xiao-ling ,LIN Ri-zong ,ZENG Ling-feng ,GAO YUAN ,LI BO




Abstract


Abstract: The blasting fragment size of a mine is required to be less than 0. 4 m. However,this area has a geological structure consisting of both hard and soft layers,which makes the traditional blasting method easy to produce boulders,and the blasting quality difficult to meet the requirements. In order to conquer the problem and save the construction cost,blasting tests on square hole layout with both deep and shallow holes were carried out with the middle shallow hole depths of 0 m,4 m,5 m,6 m and 7 m. Firstly,ANSYS/LS-DYNA finite element software was used to carry out numerical simulations with a limestone model with RHT constitutive relation in the upper part and a marl model with HJC constitutive relation in the lower part,forming a hard-soft interlayer structure. Then,numerical tests were conducted to initially obtain more optimal middle hole depths,and the distribution characteristics of rock mass damage and the distribution law of blast effective stress under different test conditions were analyzed. Since ANSYS/ LS-DYNA does not take the effect of detonation gas into account,the middle shallow hole depths of 4 m and 5 m were selected for on-site blast tests in order to obtain more accurate experimental conclusions and not to excessively increase explosive consumption. The research results show that it is effective to reduce the blasting boulder yield by square hole layout combining deep and shallow holes. When the depth of the middle shallow hole is 5m,the curvature coefficient Cc and the boulder yield can be reduced. Before the technology optimization,the average boulder yield was about 64. 4%,and the rate of fragments larger than 0. 4m have been reduced to about 38. 1% after the technology improvement,making the blast fragmentation to a favorable level. So,the scheme of 5 m shallow holes has a better effect of reducing boulder yield than the original blasting scheme and the scheme of 4 m middle shallow hole.



Key words: open pit; blasting; numerical simulation; optimization





Chinese Information


标题: “硬软夹层”条件下深浅结合方形布孔爆破技术试验研究



作者: 王皓永 ,任晓玲 ,林日宗 ,曾令峰 ,高 远 ,李 波



摘要: 某矿山控制爆破工程要求爆破后粒径小于 0. 4 m,但该区域为“硬软夹层”地质构造,采用传统爆 破方法在孔口堵塞段极易产生大块,爆破质量难以满足要求。为改善爆破质量节约施工成本,借鉴深浅结合 方形布孔技术,分别在现场工况的基础上以中间浅孔深度为 0 m、4 m、5 m、6 m、7 m 开展爆破试验研究。首 先采用 ANSYS /LS-DYNA 有限元软件开展数值模拟试验,建立了上半部采用 RHT 本构关系的石灰岩模型, 下半部采用 HJC 本构关系的泥灰岩模型,形成“硬软夹层”构造。随后在多组数值试验中初步获取相对较优 的中间浅孔深度,分析不同试验条件下岩体损伤分布特征与爆炸有效应力分布规律。由于 ANSYS/LS-DYNA 并未将爆生气体的作用考虑在内,因此为了得到更准确的实验结论,同时考虑到不宜过度增加爆破炸药 消耗,结合项目实际情况,选用 4 m、5 m 中间浅孔深度进行现场爆破试验。研究结果表明: 采用深浅结合方 形布孔的措施降低爆破大块率是有效的。采用中间浅孔深度为 5 m 时,可以降低曲率系数 Cc 与爆破大块 率。技改前平均大块率约为 64. 4%,技改后 0. 4 m 以上的大块率可降低至 38. 1% 左右,使得爆堆级配达到 良好水平。其降低大块率效果优于原爆破方案及 4 m 中间浅孔方案。



关键词: 露天矿山; 爆破; 数值模拟; 优化



Journal Integrated Operation and Management Platform with Network JMPN-2.0
Journal Integrated Operation and Management Platform with Network

《Blasting 》editorial department
Copyright © 2009   System Management   Chinese
Statistical information:total visitors Online0
putting on ICP record: E-ICP Prepared No. 05003336-9